FACTS ABOUT WORLEY HIGHWAY DISTRICT

ROAD SURFACE  
Type Miles
PAVED 95.252
GRADED GRAVEL (MILES TREATED WITH MAGNESIUM CHLORIDE) 78.965
GRADED GRAVEL  14.079
EARTH 4.348
UNIMPROVED 0.479
TOTAL MILES 193.123
     
CAPITAL IMPROVEMENT PROJECTS
     

       
WORLEY HIGHWAY DISTRICT COMPLETED PROJECTS
Project OBJECTIVE Total In-House Cost Total Contracted Cost Year Project Completion
ROCKFORD BAY RD REBUILD FROM SOLITAIRE RD TO LOFFS BAY RD $194,996.63 $18,320.00 2021
DOWER ROAD REBUILD $282,451.78 $79,077.32 2020
WATSON ROAD REMOVE ROCK OUTCROPPING $17,446.23 $50,001.25 2019
BURTON BRIDGE REPLACE CULVERT WITH BRIDGE TO REDUCE FLOODING   $210,961.03 2018
LOFFS BAY ROAD SHOULDER REPAIR REPAIR SLIDE $13,652.98   2018
CARNIE ROAD REBUILD .6 MILES FROM US 95 $170,850.43   2018
CLEMETSON ROAD REBUILD FROM MEADOWBROOK LOOP TO REYNOLDS ROAD $244,942.90   2017
TRANSPORTATION PLAN TRANSPORTATION PLAN   $57,105.43 2017
GREENSFERRY ROAD SLIDE EMERGENCY REPAIRS   $284,826.00 2017
TALL PINES/LOFFS BAY INTERSECTION SIGHT DISTANCE IMPROVEMENT $14,784.87   2017
NEW OFFICE BUILDING PROVIDE CLEAN STORAGE OF DISTRICT RECORDS   $578,363.00 2016
BLOOMSBURG ROAD IMPROVE DRAINAGE $73,321.89   2016
INTERSECTION LIGHT UPGRADE (HIGHWAY 95 & DISTRICT ROADS) REPLACE LIGHTS WITH ENERGY EFFICIENT LED LIGHTS   $20,638.00 2016
COUGAR GULCH ROAD SAFETY AUDIT   $22,573.17 2016
SIGN GRANT NEW SIGNAGE - DISTRICT WIDE $30,114.00   2014
LOFFS BAY NORTH OF SHRINER REBUILD .7 MILES $264,161.01   2013
LARSON RD PAVEMENT $48,106.89   2013
CONKLING ROAD RESURFACE -LARSON ROAD TO BENEWAH CO. LINE   $1,448,256.07 2012
ELDER ROAD RESURFACE    $1,862,690.22 2012
CAVE BAY ROAD RESURFACE 3 MILES   $863,893.47 2012
SUN UP YARD MAINTENANCE BUILDING   $154,529.83 2012
KIDD ISLAND/HULL ROAD INTERSECTION (SOUTH) RECONSTRUCTION INTERSECTION PHASE 2   $315,204.14 2011
CONKLING ROAD RESURFACE - US95 TO LARSON ROAD   $432,999.77 2011
LOFFS BAY ROAD AT MICA CREEK CROSSING ADD CULVERTS, RAISE ROAD TO REDUCE FLOODING $200,989.48   2010
PRESLEY ROAD PAVE FROM US 95 TO WENIGER HILL ROAD-1.7 M. $87,302.73   2010
KIDD ISLAND/HULL ROAD INTERSECTION (SOUTH) RECONSTRUCTION INTERSECTION PHASE 1   $119,523.46 2010
CAVE BAY BRIDGE RECONSTRUCTED  $35,444.00   2009
SETTERS RD RESURFACE $40,522.36   2008
DRECHSEL RD RESURFACE $57,799.27   2008
LARSON RD RECONSTRUCTED LESS PAVEMENT $138,119.86   2008
TALL PINES BRIDGE BUILD NEW TALL PINES BRIDGE-REALIGN TALL PINES RD TO NEW BRIDGE   $669,601.66 2008
PRESLEY ROAD REBUILD FROM US 95 TO WENIGER HILL ROAD-1.7 M. $306,224.73   2007
DOUBLETREE LANE REBUILD AND PAVE WITH TRIPLE SHOT ASPHALT   $284,810.17 2007
KIDD ISLAND RD/ VALHALLA RD DESIGN AND CONSTRUCT A NEW INTERSECTION   $155,452.74 2007
LOFFS BAY RD BRIDGE REHABILITATE BRIDGE   $192,256.00 2006
ROSE CREEK RD BRIDGE BRIDGE REPLACEMENT   $245,807.56 2006
VOGEL TO US 95 REBUILD .23 M.-CONSTRUCT 2.42 M. TRIPLE SHOT ASPHALT 2.65 M.   $948,611.00 2006
       
              
WORLEY HIGHWAY DISTRICT BRIDGES
Location Bridge Length Material Owner Year Built
BURTON ROAD        19' 10" STEEL WHD 2018
CAVE BAY ROAD           138’ R/R UNDERPASS Union Pacific 1942
CAVE BAY ROAD BRIDGE    E.  FORK  ROCK CREEK          14’ CONCRETE (WOOD FRAME) WHD UNKNOWN
   
REPLACED CONCRETE (WOOD FRAME) WITH (STEEL FRAME)       2009
CHATCOLET ROAD BRIDGE OVER S. FORK ROCK CREEK         22’     CONCRETE WHD 1952
CONKLING ROAD BRIDGE  OVER ROCK CREEK           26’ CONCRETE (FRAME) WHD 1962
DRECHSEL ROAD BRIDGE TRIBUTARY OF ROCK CREEK  UNDER 20’ CONCRETE  WHD        EARLY  1960’S
ELDER ROAD BRIDGE          OVER BOZARD CREEK         26’ CONCRETE (FRAME) WHD 1955
HAMAKER ROAD BRIDGE  OVER BELGROVE CREEK      UNDER 20’ CONCRETE (BOX CULVERT) WHD UNKNOWN
LOFFS BAY ROAD BRIDGE OVER MICA CREEK         35.5’ STEEL WHD  BUILT 1962 REBUILT 2006
MCAVOY ROAD BRIDGE    OVER COUGAR CREEK              32’ TIMBER (STRINGER/GIRDER) WHD BUILT 1940 REBUILT 1989
MILLER ROAD BRIDGE        OVER COUGAR CREEK         16’ CONCRETE WHD 1972
POIRER ROAD BRIDGE        OVER LAKE CREEK               34’ STEEL (STRINGER/GIRDER) WHD BU1LT 1950  REBUILT 1998
REW ROAD BRIDGE             OVER LAKE CREEK        20’ CONCRETE WHD 1931
REW RD BRIDGE                OVER S. FORK LAKE CREEK        11’ CONCRETE WHD 1932
ROCKFORD BAY RD BRIDGE  OVER BELGROVE CREEK   UNDER 20' CONCRETE (BOX CULVERT) WHD UNKNOWN
ROCKFORD CR. BRIDGE (WATSON RD)                    OVER ROCKFORD CREEK         42’ TIMBER (STRINGER/GIRDER) WHD BUILT 1950
ROECKS ROAD BRIDGE     OVER S. FORK ROCK CREEK            32’ CONCRETE (STRINGER/GIRDER) WHD 1990
ROSE CREEK ROAD BRIDGE OVER ROSE CREEK         47.5’ TIMBER (STRINGER/GIRDER) WHD BUILT 1960   REBUILT 2006
SUNNY SLOPES ROAD        90’ R/R UNDERPASS Union Pacific 1931
TALL PINES ROAD BRIDGE TRIBUTARY TO MICA CREEK        42’ CONCRETE WHD 2008
WILLIAMS ROAD BRIDGE TRIBUTARY TO ROCK CREEK        21’ TIMBER (STRINGER\GIRDER) WHD 1940